Main Street bridge deck poured; sidewalk, lighting and parapet work next
Summary
Council heard a construction update: bridge deck poured March 21; sidewalk removal and temporary access plans underway; conduit and street-lighting bases to be installed; parapet forming and pours expected to take about one week per side plus curing time.
Get email alerts on the Infrastructure Construction topic
No spam. Unsubscribe anytime.
City staff provided a construction update on the Main Street bridge project, reporting that the bridge deck was poured on Friday, March 21, and is currently curing to reach required strength.
A presenter identified as Mr. Beyer said roadway grading and curb work were completed on the Water Street side of the bridge; a subcontractor will remove and repour the south-side sidewalk between the river and First Street while maintaining temporary access for businesses and residents. Mr. Beyer said another subcontractor will install conduit and street-lighting bases this week, and that crews will begin forming the bridge parapets (concrete railings) next week.
Beyer described a roughly two-week cycle for each parapet side: one week for forming, rebar and concrete pouring, then about another week for curing, weather permitting. He said updates will continue as the project progresses and invited council members to ask questions.
Why it matters
The update outlines near-term traffic, pedestrian and business-access work on a downtown bridge project. Temporary access plans and a defined parapet schedule provide local businesses and residents a short-term timeline for expected impacts.
What council received
Mr. Beyer reported the contractor and subcontractor schedule and confirmed temporary access will be maintained during sidewalk removal and repouring. Council members offered no substantive amendments to the schedule during the briefing.