Summary

Public Works presented a list of urgent and planned water/wastewater capital repairs — many previously funded by ARPA — and said a consultant’s rate-and-allocation study will be available for a deeper commission discussion on rate increases (current presentation assumes 4%).

Public Works Director Dan Mattson briefed commissioners on the water and wastewater FY26 requests and a recent consultant rate-and-allocation study. Staff said the FY26 utility budgets in the presentation assume a 4% rate increase (the county can choose otherwise) and noted that ARPA had funded over $3 million of prior repairs, creating a correction in FY26 if that federal funding is not repeated.

Mattson walked through a list of major repairs and capital asks that together drove the large percentage increases in the utilities budget. Items highlighted as urgent or high priority included:

- Wharton Wastewater Treatment Plant solids press installation (installed equipment purchased with ARPA; installation budgeted at about $375,000, FY25 rollover). - Kennedyville Pump Station No. 2 replacement (total project ~ $922,800; staff anticipated about $575,000 in developer allocation fees, leaving a county ask in the presentation of roughly $350,000). - Fairlee Well No. 2 replacement (presenter said rehabilitation proved infeasible and the well needs full replacement; cost presented: ~$835,500). - Tollchester wastewater plant UV disinfection replacement (~$175,000) and multiple actuator/valve replacements (noted $52,000 for several valves this year). - Water-tower maintenance across county tanks: a consultant inspection identified about $2.4 million of tank work; staff proposed phasing that across roughly six years (~$400,000/year) to address coatings, corrosion and safety requirements.

Other requests included continued grinder-pump replacement and maintenance (many grinder pumps have exceeded their expected life), an annual pump-station pump-replacement program (~$30,000), targeted security cameras at high‑priority pump stations (~$8,000 for eight cameras) and expanding GIS mapping to additional systems (~$60,000). Mattson noted some projects are rollovers from FY25 and others depend on developer funding or could be deferred, but emergency repairs are costlier and risk service disruption or regulatory noncompliance.

Mattson asked commissioners to reserve time in the next workshop for a detailed session with the consultant who completed the rate-and-allocation study so the board can consider phased rate increases, subsidy impacts and capital funding options.

Ending

Staff recommended a focused follow-up with the rate-study consultant and said some capital items are time-sensitive; commissioners agreed to schedule a detailed discussion to evaluate rate scenarios and capital priorities.