Lakewood Road sidewalks project cost rises to about $3.2 million; committee backs fund allocation
Summary
Staff reported an increase on the Lakewood Road sidewalks project from roughly $2.0 million to about $3.2 million, citing unanticipated signal upgrades and safety protections; committee moved to recommend additional funds.
Get email alerts on the Sidewalks And Pedestrian Safety topic
No spam. Unsubscribe anytime.
Staff reported a substantial cost increase for the Lakewood Road sidewalks project, with the new price described at approximately $3,200,000, up from about $2,000,000.
Kevin explained the change reflected unanticipated signal upgrades at Mulcuit Road required by District 4—adding pedestrian push-button improvements—and additional safety protections where the sidewalk passes next to a reservoir. "The new signal upgrades need to be done for pedestrian buttons and things related to that nature as required by District 4," Kevin said.
A committee member asked about timing; Kevin said staff were aiming to finish design and begin construction by the end of the calendar year. Members asked whether the project was fully designed; staff replied the project was in final design review and needed DOT review by the district's unit in Newington.
A motion to recommend allocation of additional funds for the change was made and seconded; the meeting record shows the motion was moved and seconded and members voiced approval. The committee forwarded the recommendation for funding adjustments; staff will follow up with design and DOT review steps.
The record does not include a detailed cost breakdown or the exact contingency/funding source for the additional $1.2 million; staff indicated further details would be available during design review and in subsequent reports to members.