Okaloosa pursues Triumph funding after confidential manufacturer selects Shoal River Ranch site
Summary
County commissioners authorized a Triumph Gulf Coast application for a confidential company proposing a phased, multi‑phase manufacturing campus at the Shoal River Ranch ‘giga site,’ a project county and economic‑development officials say could exceed $1 billion and create hundreds of higher‑paying jobs.
Get email alerts on the Economic Development topic
No spam. Unsubscribe anytime.
Okaloosa County commissioners voted unanimously Tuesday to let the county apply to Triumph Gulf Coast for an infrastructure grant to ready 135 acres at the Shoal River Ranch “giga site” for a confidential manufacturer that has selected the site for a phased, 1,000,000‑square‑foot aircraft systems campus.
The board’s action launches the first step of Triumph’s three‑part review process, county officials said, and clears the way for a Triumph board review on April 23. If negotiations progress, officials said Triumph could consolidate later term‑setting steps and a grant award as early as June.
County economic‑development officials said the firm’s initial buildout would be 250,000 square feet with a required completion date by December 2026, a second 250,000‑square‑foot phase by the end of 2028 and remaining capacity through 2036. Nathan Sparks of 1 Okaloosa Economic Development Council told the board the total private investment could be about $1,040,819,000 and the project would create 336 jobs with average pay above the county’s current wage.
Why it matters: county staff and partners told commissioners the site is already publicly owned and that Triumph funding would pay for public infrastructure — roads, water/sewer extensions, stormwater and security — needed to support the manufacturer. Triumph Gulf Coast has indicated conceptually it could award up to $50,000 per job; at 336 jobs that equates to a potential $16.8 million, Sparks said.
What commissioners discussed: commissioners praised long‑term site preparation and emphasized urgency. Several commissioners and staff noted Shoal River Ranch work dates back to a 2018 policy decision and earlier grant awards. Commissioners asked about the county’s financial exposure; county staff and EDC representatives said the performance guarantee and any clawback language would be negotiated between Triumph and the company and that, under current drafts discussed with Triumph, the private company — not the county — would carry the primary clawback liability. If legal action were required to recover funds, the county could share limited legal costs under the negotiated terms, they said.
Next steps: staff said the county will submit the Triumph application this month, pursue term‑sheet negotiations if Triumph advances the request, and return to the board with any proposed ground lease and final grant agreement for approval before any award is accepted.
Speakers quoted in this article are limited to those who addressed the board during the Shoal River Ranch presentation and subsequent discussion.