Ocean Shores committee to seek Transportation Benefit District changes for road repairs and striping
Summary
Staff told the finance committee they will present a material change order to the Transportation Benefit District (TBD) plan to fund pavement cutouts and overlays and other items such as striping, shifting work from the general fund to TBD funds where eligible.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
City staff said they will pursue a material change order to the city’s Transportation Benefit District plan to add a set of prioritized road cutouts and overlays and other eligible work, moving those expenses from the street/general fund to TBD funds where legal requirements are met.
Why it matters: Staff identified roughly $38,610 in candidate pavement repairs that could be paid from the TBD rather than the street fund. Staff said some recently contracted striping work — a $61,000 job that was later re‑done at no charge because of quality issues — had been paid from the general fund but could have been eligible for TBD funding under the TBD’s project criteria.
Details: Sarah said the TBD board is the city council but operates through separate hearings and required meetings. Because prior administrations did not always route projects through the TBD’s required meetings, staff will bring a material change order back to the TBD board (council meeting in its TBD role) and may return multiple times as the public‑works committee refines projects and priorities. Alex Severson, the city’s street lead, was cited as the staff contact who compiled proposed cutouts and overlays for 2025.
Next steps: Staff will bring a “baby” material change order to council (acting as the TBD board) and will continue to coordinate with the public works committee to identify projects that meet TBD criteria, including improved safety, reduced risk of facility failure, and improved connectivity.
Ending: Committee members asked staff to proceed with the TBD material change order and to present supporting cost estimates at the next public works meeting before a TBD hearing.