District to advertise phase 1 bids for major campus rebuild; demolition, asbestos abatement and GMP expected this year
Summary
Construction staff told the board the district will advertise phase 1 bid packages in March–April, seek a guaranteed maximum price (GMP) for phase 1 in May, start heavy summer site work as early as June 1, and address asbestos in limited materials before demolishing Buildings 7 and 16 and the pool.
A district construction representative told the school board the project to rebuild the campus is moving into phase 1 and that the district received phase 1 bid documents about a week before the meeting. The plan is to advertise scope packages in March and April, satisfy statutory advertising requirements and bring a guaranteed maximum price for phase 1 to the board in May.
Scope and schedule: the phase 1 work will include demolition of Buildings 7 and 16, removal of the pool structure, site setup and fencing to separate construction from operating areas, and limited asbestos abatement. The construction representative said crews aim to start heavy construction site work by June 1 so the site is ready by the August school start; the timeline will be tight and that start date is the goal for meeting long lead items.
Asbestos abatemen…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat