City updates capital projects: AMI meter rollout set to begin, Proximity Park tower near completion

2829573 · February 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City manager and staff updated commissioners on capital projects: Proximity Park water tower nearing completion, AMI meter deliveries in hand with installations planned to start next week, Phase 3 commercial metering, Pin Oak pump station delivery in March and commission room/HVAC upgrades in progress.

City Manager Silcock gave a status update on multiple capital improvement projects, including the Proximity Park water tower, automated metering infrastructure (AMI) rollout, Pin Oak pump station and commission room upgrades.

Proximity Park water tower: Silcock said the tower is about 90% complete; remaining items include final remediation and high‑pressure pump installation at the water facility. Once the pump is installed staff expect to bring the tower fully online in the first quarter of 2026.

AMI meter rollout: The city has received all ordered residential meters (approximately 2,600 meters were ordered in January 2024 with a long delivery lead time). Staff reported the meters had some initial programming issues but are now ready; installation is planned to begin next week with an estimated throughput of roughly 75–100 installs per week and expected completion in Q3 2025. Residents will be notified before crews visit their property; Silcock said installations will occur during normal business hours by city personnel wearing city identification.

Other projects: The Pin Oak pump station equipment has been ordered with expected delivery in mid‑March and a short work schedule to follow. The water plant generator project is roughly 90% complete with transfer switch schematics remaining; staff expect Q4 2025 completion. Commission room and HVAC upgrades are underway; the city is resolving subcontractor and design issues and will provide firmer timelines when available.

Impact for residents: Silcock indicated residents should expect brief meter interruptions during replacements and will receive advance notice. The city also plans public messaging about the outage map and meter benefits.

Ending: Staff will continue monthly reporting on capital project schedules and will provide more detailed timelines as installations and deliveries firm up.