City manager gives overview of active capital projects, AMI meter work underway
Summary
City Manager Silcott provided an overview of active capital projects including the Proximity Park tower, water plant upgrades, AMI meter installations and a commission chamber technology upgrade; timelines and percent-complete figures were reported.
City Manager Silcott briefed the Ottawa City Commission on March 19 about active capital improvement projects and near-term milestones, reporting progress on multiple infrastructure efforts.
Silcott said the Proximity Park water tower and water pump plant upgrades are in progress (tower and pump delivery items remain) and noted the tower project was about 62% complete with a projected completion in the first quarter of 2026. The water plant generator…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat