Summary

Staff briefed the board on a proposed code amendment to align local permit timelines with the Senate Local Project Review Act. The planning commission held a public hearing and voted 7–0 to forward the amendment; the board scheduled a public hearing for early April and agreed to keep the county's 120-day general cap for type 3 permits.

County planning staff told the Board of Commissioners on March 17 they will propose an amendment to county code to align permit processing timelines with the Senate Local Project Review Act and related state rules.

Why it matters: The state law sets maximum processing times for different permit categories; local code must reflect or reconcile with state-mandated timelines. The amendment sets specific timeframes for Type 1 and Type 2 permits and contemplates the state-allowed limit for Type 3 permits.

Planning staff explained the proposed changes: Type 1 permits (simple boundary-line adjustments) would be processed within 65 days; Type 2 permits (short plats and minor alterations) within 100 days; and the county may adopt up to 170 days for Type 3 permits, though staff and commissioners agreed to keep the county's existing 120-day general limit for most land-use permits. Planning staff said the proposed numbers are consistent with the new state law and that the county's current practice generally meets the timelines.

The planning commission held a public hearing and voted 7–0 to forward the amendment to the board. Commissioners asked staff about internal metrics and whether the county tracks average processing time versus state timelines; staff said Tyler's permit system reports application-to-issuance times but does not automatically stop the clock for back-and-forth information requests, so staff maintain separate timelines in staff reports.

Outcome and next steps: The board set a public hearing for the ordinance amendment on April 8/9 (announced for board-level hearing) and directed staff to publish the hearing notice. Commissioners signaled they prefer to retain the county's 120-day general cap for Type 3 permits rather than adopt the full 170 days available under state law.

Staff said they would return with the public-notice materials and staff report for the board hearing.