Utilities director warns of major capital needs: PFAS, AWT and deep-injection wells drive projected $700M-plus work plan

2827289 · March 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Brevard County Utilities described a broad capital program driven by federal/state water rules and nutrient/BMAP requirements that will require bonds, connection-fee updates and higher rates to fund advanced wastewater treatment and deep-injection disposal.

Brevard County Utilities staff told commissioners on March 27 that new federal and state rules, rising construction costs and nutrient-reduction requirements in Basin Management Action Plans (BMAPs) have produced an estimated $700 million-plus capital-improvement program over the coming decade.

Presenter Eddie (utilities presenter) described six service areas with separate systems, roughly 1,100 miles of pipe, more than 320 lift stations and multiple treatment plants. He told the board that some existing wells have detected PFAS above the federal four parts-per-trillion screening metric in areas including South Brevard and Mims and that removal typically requires reverse osmosis (RO), which creates a brine stream that, under state rules, is often disposed of via deep injection wells. He said state rules require redundancy for deep injection wells because labs require periodic shutdowns for testing and that a single well must typically be paired with another well by 2032 to meet intended 0-discharge timelines.

The presentation listed several ongoing and planned projects: a new South Brevard water/wastewater plant with RO for PFAS removal; advanced wastewater treatment (AWT) upgrades required in BMAP areas; a South Beaches wastewater project (with an estimated $50M construction cost); North-Brevard and Mims upgrades; and space-related infrastructure coordination on Port St. John and nearby areas. Eddie said that the department has pursued alternative funding successfully — six FDEP grants since 2022 (about $33 million), ARPA funds and other state appropriations — to leverage projects and reduce the direct rate burden.

Eddie said the department is conducting a connection-fee study and expects to bring recommendations to the board; he explained that connection fees (one-time charges for new capacity) can be used on expansion projects and are distinct from recurring user-rate revenue. He said Barefoot Bay is a dependent district with separate accounting and higher per-customer rates because it cannot participate in the countywide financial model for large projects.

Commissioners asked about timelines for the connection-fee study and about whether the department would have numbers for the board to review; Eddie said he expected study results after the June recess. No votes were held during the presentation; staff said future bond approvals and rate adjustments would come to the board as projects and studies are finalized.