Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Government center renovation near completion; project $249,000 over estimate, officials say
Summary
County staff reported progress on the Government Center renovation — boilers and air handlers installed, punch-list walk-throughs underway — and said the project is running about $249,000 over an earlier estimate, with some contingency already spent.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Polk County project staff told the Board of Supervisors that work on the Government Center renovation is progressing and remains on track for completion despite modest cost overruns.
Presenters said the building’s boilers were started, roof air handlers were scheduled for installation the next day, and a punch-list walk-through had begun. Long-lead items including a generator and card-swipe hardware were still pending; work on glass and door hardware also continued.
On costs, staff reported the project was about $249,000 over the estimate (described as about 2–3% over). That number reflects a combination of additional change orders — the largest identified as added door hardware and lock devices — and smaller credits for work not performed, such as eliminating a chain-link fence. The presenters said contingency funds have been used and that the project team is tracking credits and change orders to narrow the variance.
Officials said the project team remained confident the work would move forward with minor punch-list items and continued equipment deliveries. The board was briefed on next steps and the team’s plan for final closeout activities.

