Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
County accepts Century Hall work and approves final payments to contractors
Summary
The board accepted completed work at Century Hall and approved final payments totaling $42,819.02 to multiple contractors from the fairgrounds capital budget.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
McLeod County approved final acceptance of work and final payments for the Century Hall building project, directing $42,819.02 from the fairgrounds capital budget to multiple contractors.
In the county’s summary, payments included $9,991.20 to R and R Excavating of Hutchinson; payments to Voss Plumbing and Heating of Painesville of $8,181.00 and $13,955.00 (two line items listed); $1,255.00 to Grazini Brothers and Company; $3,020.00 to Breath Senz and Fire Protection; and $6,416.75 to Design Electric. County staff recommended final acceptance, stating the contract items under scope had been completed satisfactorily.
Motion and vote: A commissioner moved to approve final acceptance and payments; the motion was seconded and carried by voice vote.
County staff recorded final acceptance and will close out the related contracts and accounting for the fairgrounds capital budget.

