Terminal rehab escalators and roof complete; Taxiway J work to close a runway through August

2810431 · March 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Airport staff reported progress on terminal rehabilitation—escalators and roof work nearly finished—and said construction on Taxiways J‑1 and J‑2 recently entered a phase that will close a runway through about August for work connecting taxiways.

Airport staff told the Laredo Airport Advisory Board on March 1 that the terminal rehabilitation project has reached several visible milestones: both passenger escalators are now operational and roof replacement is substantially complete. Staff said finishing touches…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans