Terminal rehab escalators and roof complete; Taxiway J work to close a runway through August
Summary
Airport staff reported progress on terminal rehabilitation—escalators and roof work nearly finished—and said construction on Taxiways J‑1 and J‑2 recently entered a phase that will close a runway through about August for work connecting taxiways.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Airport staff told the Laredo Airport Advisory Board on March 1 that the terminal rehabilitation project has reached several visible milestones: both passenger escalators are now operational and roof replacement is substantially complete. Staff said finishing touches (gutter work and cleaning) remain and that the terminal’s appearance has markedly improved.
Staff said generator replacement work is ongoing. On airfield construction, staff reported the next phase of Taxiway J‑1 and J‑2 work began the previous week and that one runway will be closed for construction through roughly August while crews finish the taxiway connections; the airport will maintain operations on the remaining runway, staff said.
Board members asked for updates on project schedule and impacts to operations. Staff said the projects are progressing “on schedule,” and emphasized they will coordinate with FAA and operations to minimize disruption.
No formal action or vote was required; staff said it would continue to brief the board on construction progress and any operational notices to the flying public.