Commissioners approve $61,232.87 change order for Polk County courthouse restoration
Summary
A change order to address second‑floor millwork modifications and a basement leaking wall was approved; the work will be paid from the courthouse restoration fund using surplus depository interest revenues.
Get email alerts on the Capital Projects Restoration topic
No spam. Unsubscribe anytime.
Polk County Commissioners on March 25 approved change order 008 for the courthouse restoration project totaling $61,232.87.
County staff said demolition revealed a leaking wall in the basement where an old elevator had been removed and additional repairs and millwork modifications on the second floor are required to protect structural integrity and prevent further water intrusion. The court approved using surplus depository interest revenues held in the restoration projects fund to cover the expense.
Commissioners approved the change order by voice vote and directed staff to proceed with the repairs.