Commissioners open bids for bridge and structure projects, ratify state grants and acknowledge upcoming State Road 32 closure
Summary
The Boone County Board opened bids for several bridge and small‑structure projects, took the bids under advisement, ratified Community Crossings matching grants for two projects, approved an NDOT local‑detour acknowledgment for an upcoming State Road 32 closure and ratified several INDOT reimbursement agreements and inspection contracts.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Boone County commissioners opened competitive bids for multiple road projects, took the bids under advisement, and ratified state and federal grant agreements tied to those projects during the March 10 meeting.
Bids opened: For Project 2022‑07 (Boone County Bridge No. 44 rehabilitation near Bridgeport) the board read three bids: Milestone Contractors LP ($438,700), Duncan Robertson, Inc. ($477,368.10) and E&B Paving, Inc. ($488,065.08). For Project 2023‑08 (replacement of small structure EA‑021 / Pine View Drive small structure) the board opened multiple bids including Milestone Contractors ($397,700), Fox Contractors ($414,706), Crackers Demo ($645,768), Kindred Excavating Group ($312,165.09), Morphy Construction ($610,675) and Codex Co. ($424,835). The board moved to take those bids under advisement pending review of qualifications, funding and low‑bid calculations.
Grant ratification and NDOT acknowledgments: Commissioners ratified two Community Crossings Matching Grant (CCMG) agreements tied to the bid projects: DES ending in 111 for Bridge 44 (maximum match awarded $204,750) and DES ending in 112 for Pine View Drive (award $222,500). Staff noted CCMG pays 50% of eligible construction costs up to the awarded maximum and the actual reimbursement will be based on the low bid and eligible costs.
The board also approved an NDOT “unofficial local detour” acknowledgment related to a planned short‑term closure of State Road 32 (between State Road 75 and 1175 West) for multiple small‑structure replacements beginning April 7; the planned closure is expected to last about 20 days. County staff explained that local traffic often diverts onto county roads (for example, County Road 100 South and 1175 West) and that the acknowledgment allows the county to seek reimbursement from INDOT for damage or costs incurred on that unofficial detour route.
Other NDOT/INDOT items ratified included a construction agreement for Bridge 162 (DES 2301599) on County Road 500 South and an INDOT Local Public Agency (LPA) reimbursement agreement for the county’s four‑year bridge inspection program; both items were ratified as standard state grant/administration agreements. The board also approved a task order for construction inspection services (BFS Task Order 56) for a fiber installation project, not to exceed $35,000, to be reimbursed by the utility applicant.
Why it matters: The bids and grant ratifications are the procurement and funding steps that enable bridge rehabilitation and small‑structure replacements included in county capital plans. The State Road 32 closure will affect local traffic patterns and county roads for several weeks.
Votes and procedural notes: Bids were taken under advisement for later award; grant and INDOT/NDOT agreements were ratified by voice vote. Commissioners asked staff to return recommended award actions once bid review and fund matching calculations are complete.