Commission halts work at 36 Nicole Terrace, schedules erosion-control follow-up on April 14
Summary
Contractor work at 36 Nicole Terrace proceeded into flagged wetlands; commission ordered erosion controls and postponed the case to April 14 for a remediation plan and inspection.
Get email alerts on the Wetlands Violation Nicole Terrace topic
No spam. Unsubscribe anytime.
Contractors who began removing logs and chipping brush at 36 Nicole Terrace were ordered to stop after the commission found damage and inadequate erosion controls; the commission continued the matter to April 14 and instructed the property team to install silt socks and a silt fence before any further work.
Why it matters: The work affected flagged wetland boundaries and the commission said earlier remediation steps must be documented and reviewed before more activity. Commissioners said removing material from the wetland without full erosion controls can cause damage that requires repair and could lead to fines.
At the hearing, property representative Ashfa Aziz and contractor Chris described the work already completed and said they intended to remove logs and chip brush. Justin, the city conservation inspector, said the contractor began chipping before erosion controls were fully in place and that blue boundary flags were on the ground when the crew worked. Chris said crews stopped immediately when instructed and that SMM (an erosion-control contractor) is scheduled to install containment on April 4: “It's gonna be the mulch, socks with a 2 foot, silken, about 600 feet… 1 straw and we want it dug in 6 inches at the bottom of the silt fence.”
Commissioner Mary Anne (commission staff) directed the contractor to stop work, inspect the site and wait for Mary Anne’s direction on how to remove wood chips already in the wetland. The commission member warned that continued work could trigger fines: “When are you gonna be back in Nothing. No. Nothing. We if you start working, I'm gonna start assessing fines.”
Action taken: The commission voted to continue the 36 Nicole Terrace matter to April 14 to allow installation of erosion controls and to receive a remediation plan and photographs documenting the site prior to additional work.
Next steps: The contractor and property owner must install erosion controls on April 4 as described and submit the details to Justin. The commission asked Mary Anne to attend the April 14 meeting to give further direction and to review the corrective measures.