Committee hears update on Priority 1 school construction; staff says group 1 could start in spring
Summary
Committee on Joint School Buildings received a progress report on Priority 1 projects (Hillside, McLaughlin, Parkside, Southside and Beach Street). Staff outlined issued design documents, procurement status and a mid‑March culvert survey for the Beach Street site; the committee accepted the monthly financial report.
Members of the Committee on Joint School Buildings heard an update on the school district’s Priority 1 construction projects and accepted the committee’s monthly financial status report at a regular meeting.
The presentation outlined recent design and procurement milestones for Group 1 (Hillside and McLaughlin), ongoing work on Group 2 (Parkside and Southside) and site planning for the Beach Street project at Sheridan Park. Project staff said 75 percent construction documents for Group 1 were issued late last month, that power issues at modular locations had been resolved and that exploratory work on fire protection systems at Hillside and McLaughlin is complete.
The update matters because these projects include full campus construction and site work that will determine when heavy construction begins and how…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat