District updates board on capital project progress; high school technology slab poured, tall light poles arriving
Summary
Construction managers told the Gates Chili Board of Education on March 25 that phase 1 of the district capital project is nearing middle‑school turnover, high‑school technology construction has a concrete slab in place, and phase 2 site grading and foundations are underway.
Get email alerts on the Infrastructure Capital Projects topic
No spam. Unsubscribe anytime.
District construction staff gave a March 2025 capital-project update to the Gates Chili Board of Education on March 25, reporting progress on phase 1 turnover, early site grading in phase 2 and initial billing figures.
Presenters said phase 1 work has focused this month on middle school spaces that are prepared for turnover next week, and crews will begin moving the district’s middle school functions the following week. At the high school, work on the technology/shop addition reached a milestone when crews poured the concrete slab for the technology space; roofing and mechanical, electrical and plumbing rough‑ins were also under way.
Contractors installed casework, specialty equipment and compressed‑air reels in technology rooms. A district representative said the wood‑shop spaces will be fitted with dust collector connections for each machine. For site work in phase 2, the district reported grading for a new softball field, foundations formed for the Florence Brasser main‑office addition and ongoing drainage and earthwork. The district noted tall field‑lighting poles are arriving; the tallest pole will be about 110 feet.
On project finances, presenters said the district is 67% billed for phase 1 work and about 8% billed for phase 2; the contingency overall had not changed and roughly $143,000 in allowances had been expended. Looking ahead, presenters said April work will focus on finishing roofing at the high school technology space, starting brick facade work, finishing ductwork and installing dust collection equipment and lighting so the space can be used for instruction.
Board members asked for follow‑up documentation at future meetings as phase 2 design phases are prepared for State Education Department (SED) review. Presenters said the next SED submission for the 2025 capital plan is slated for April, with subsequent stakeholder meetings and a December submittal planned for the next design package.
Less critical detail: the presentation included photos of the slab, mezzanine and field earthwork and noted phased stakeholder meetings and SED scheduling.