Committee adopts statewide flood-control priority list with seven projects totaling $83 million-plus in benefits

2764826 · March 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

DOTD presented and the committee approved a statewide flood-control recommended construction program that lists seven projects (five new) and a total expected benefit of over $83,000,000.

The Joint Committee on Transportation on March 24 approved the Statewide Flood Control Program recommended construction list, a slate of seven projects DOTD said would deliver an expected benefit of more than $83,000,000.

Lucas Shines, a DOTD representative, presented the recommended construction program and said there were no changes from the previous week. He described the slate as seven projects: five newly recommended projects in three rural funding districts and two projects in the urban program.

Nut Graf: The committee adopted the recommended flood-control list after DOTD’s presentation. DOTD characterized the slate as a mix of rural and urban flood-control investments with an aggregate expected benefit exceeding $83,000,000.

Details: Shines said the seven projects include five in rural funding districts and two urban projects; DOTD did not provide line-item budgets for each project during the meeting. Senator Price moved approval; the chair recorded no objections and declared the program approved.

Ending: The committee approved the flood-control priority list and then considered committee minutes and other business.