Board briefed on plan to remove hazardous tartan and replace high-school gym floor; bidding to follow

2750077 · March 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff told the board the high-school gym floor shows uneven spots caused by disintegrating underfloor discs placed over an old tartan surface; removal of hazardous tartan (mercury-containing) and subsequent bidding for a new wood floor will be required.

Business-services staff told the board the high-school gym floor is deteriorating because a former tartan surface remains beneath the current wood floor and the underfloor discs used to create a sprung surface have started to disintegrate.

The superintendent said the remediation will occur in two steps: first a hazardous-materials contractor must remove the remaining tartan — which the presentation described as containing mercury and therefore requiring specialized abatement and ventilation controls — then a flooring contractor will install a new wood floor. The district intends to advertise the project for bids and perform related small renovations such as adjusting bleacher clearance and adding a shot-clock compatible scoreboard as part of the work.

No contract awards were approved at the Jan. 13 meeting; the board was briefed and staff said they would move to advertise for bids and follow the district procurement process. Board members asked about bleacher clearance and safety; staff described planned adjustments to back bleacher seating to improve floor clearance and spectator sightlines.

Staff emphasized the schedule and phased approach: hazardous-material removal first, then flooring installation once the concrete slab is cleared. The board voted that day on related business-service items (server support, MOUs, reimbursements) but did not vote on the gym-floor project itself.