Committee awards truck chassis and approves road-maintenance contracts; motions carried

2746494 · March 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee accepted a bid from Truck Country for a truck chassis, selected Barnard Asphalt/Flint Hills for seal-coat oil, and approved metal culvert purchasing from longstanding suppliers. The campus bridge contract was awarded to Larson Construction; a resolution to authorize payment will follow.

The Richland County Public Works Committee approved a package of procurement decisions affecting fleet replacement and road maintenance.

On truck chassis, the committee awarded the contract to Truck Country for a chassis bid reported at $161,008.25. Staff had presented bid results from Lakeside International (lowest price but a new, unproven engine model), High State Truck Center (higher price but established relationship) and Truck Country. Committee discussion cited delivery timing, vendor experience and parts commonality as considerations. A motion to accept Truck Country’s bid was moved and seconded and the chair called the motion carried.

For seal-coating oil, staff received two primary bids: a joint Barnard Asphalt/Flint Hills bid at $2.61 per gallon and another vendor (MIGS) at $2.97 per gallon for the planned 45,000 gallons. Staff recommended awarding to Barnard/Flint Hills for a total cost of $117,450; the committee approved that recommendation.

On culverts, staff recommended continuing to purchase metal culverts from True North Steel and Contact Engineering, noting roughly a $1-per-foot savings relative to alternatives and stable pricing from the suppliers. The committee approved locking in pricing for one year and ordering as needed rather than stockpiling inventory.

On campus infrastructure, staff said the campus-bridge contract was awarded to Larson Construction at about $523,000 after disqualifying the low bidder for lack of relevant bridge experience; the vendor expects to start late this month pending permits and a resolution will be presented to authorize payment upon completion.

Votes at a glance

- Truck chassis: Motion to accept Truck Country bid for truck chassis at $161,008.25 — motion moved and seconded; chair stated the motion carried.

- Seal coat oil: Motion to award 45,000 gallons to Barnard Asphalt/Flint Hills at $2.61/gallon (total $117,450) — motion moved and carried.

- Culverts: Motion to recommend and lock-in purchasing metal culverts from True North Steel/Contact Engineering for one year and order as needed — motion moved and carried.

- Campus bridge: Contract awarded to Larson Construction (~$523,000); staff to present a resolution to the board to authorize payment upon completion.

Committee members asked staff to confirm delivery dates, written delivery guarantees where possible, and to note any warranty or engine-model risks (several members cautioned about an unproven new engine model offered by the lowest bidder). Several members said past delivery reliability and vendor relationships were a key factor in choosing among otherwise similar bids.

No dollar-amount amendments were made at the meeting; staff were directed to proceed with award paperwork and to return any written guarantees or additional details to the committee.