Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure Fire Station topic
No spam. Unsubscribe anytime.
Select Board hears update on fire station project; architect targets late summer/early fall
Summary
Members heard progress updates on the proposed fire station—site work, curb cuts and architectural drawings are underway—and discussed procurement timing amid tariff concerns for building materials.
Get email alerts on the Infrastructure Fire Station topic
No spam. Unsubscribe anytime.
Select Board members received a project update on the proposed fire station, including site-preparation work and an architectural schedule from Katie Sutherland.
According to the board’s discussion, Joe D'Arusso will formalize curb cuts and remove pavement next week. Architect Katie Sutherland told board members she expects to provide a schedule and a proposed budget “by the end of this week or the beginning of next week,” and she said she was targeting a late-summer to early-fall construction cycle unless the board asks to expedite it.
Board members discussed procurement timing and expressed concern about tariffs on imported materials. One member said contractors have warned that tariffs could raise costs “10 or 15 percent” and that a potential 250 percent tariff on some products would be “a whole different ballgame.” Members said they hope to move faster if possible to avoid anticipated tariff increases.
The board directed staff to coordinate with Fieldstone (land-use consultants previously engaged for site work) to produce drainage plans and engineering components needed for bidding.
No formal action was taken on the project at this meeting; the board asked staff and consultants to return with schedules, budgets and engineering plans for future approval.

