Council approves zoning, contracts and roadway financing in unanimous votes
Summary
At its March 20 meeting the Stowe City Council adopted a series of ordinances and resolutions: site approvals and variances for two development projects, contracts for construction and IT services, and short-term notes to finance three major public works projects.
Get email alerts on the Municipal Governance topic
No spam. Unsubscribe anytime.
Stowe City Council on March 20 adopted multiple measures including site approvals for two commercial developments, contracts for project and IT services, and short-term borrowing to fund major roadway projects.
The actions move several planning items and capital projects closer to construction and authorize city staff to execute contracts the administration says are needed to keep work on schedule.
Most measures were adopted after roll-call votes or unanimous voice votes. The council approved: (1) site-plan and lot-split approvals and variances for a manufacturing/warehouse project on Campus Drive (resolution 2025-088); (2) a conditional zoning certificate with variances for a Suncrest Gardens satellite operations site at 4811 Scarlet Lane (resolution 2025-089); (3) a $48,700 construction-management contract for the First Responders Memorial with Jolin Management (ordinance 2025-084); (4) contracts for off-site backup services (AetnaPlus) and city meeting software (Granicus); and (5) the issuance of three short-term notes to finance State Route 91 reconstruction, the Kent Road traffic signal project on State Route 59, and a $400,000 note related to the planned driving-range property.
Council members recorded approval during roll calls for the adopted ordinances and resolutions; the meeting transcript records the measures as passed and placed into effect according to their terms.
Votes at a glance: - Resolution 2025-088 (Campus Drive lot split / site plan / variances): moved to council by the Planning Committee and adopted by council (outcome: approved). - Resolution 2025-089 (4811 Scarlet Lane — conditional zoning certificate / outdoor storage / fleet storage variances): moved to council and adopted (outcome: approved). - Ordinance 2025-084 (contract with Michael Diewart DBA Jolin Management Services LLC for construction management — $48,700): adopted (outcome: approved). - Ordinance 2025-086 (AetnaPlus off-site backup services contract): adopted (outcome: approved). - Ordinance 2025-087 (three-year contract with Granicus LLC for agenda/meeting software): adopted (outcome: approved). - Ordinance 2025-090/91/92 (short-term notes in anticipation of bonds for driving-range land and ODOT projects including State Route 91 Darrow Road and State Route 59 Kent Road signal work): adopted (outcome: approved).
Notes: The transcript shows each measure called, moved and seconded and recorded as passed; where the transcript did not record exact numeric tallies it records the results as adopted. For full vote records please see the official council minutes and the certified roll-call sheets on the city clerk’s page.