Board’s building and site subcommittee closes month with credits; board to award summer work including Dakota High glazing and kitchen equipment
Summary
District staff told the building and site subcommittee that December change‑order activity was mostly credits and that they will recommend awarding three contracts for summer 2025 work including replacement of roughly 33 glass‑block openings at Dakota High School, upgrades to auditorium lighting and emergency systems, and replacement of two steam
The Chippewa Valley Schools building and site subcommittee met Jan. 13 and reviewed a December change‑order summary and a recommended set of summer 2025 contracts that will be on the board agenda.
Change orders and credits Jeff Atkins, presenting for facilities, said there were about 16 change orders for the month of December: 10 tied to bond projects, five to the school safety and security grant, and one technology item. “Majority of those are credits,” Atkins told the subcommittee, and he said the net savings will return to the bond program or…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat