Construction manager gives update on Whitnall referendum projects; schematic design completed and geotechnical work scheduled

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

CG Schmidt and district staff reported the referendum construction program is on schedule: schematic design was completed in February, design development is expected in May, geotechnical studies will occur over spring break, and budget checks are underway to align costs with the referendum.

CG Schmidt representatives and Whitnall School District staff told the board that the district’s referendum construction program is advancing on schedule, with key design milestones and budget validation underway.

Ryan Schmidt, managing director of CG Schmidt, introduced himself and a colleague and said the firm has partnered with Whitnall on past projects, including the district’s original high school more than 60 years ago. “We’re extremely excited…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans