New Beltrami County jail moves to construction permitting; plan-review approvals completed
Summary
Design and construction teams reported completed state plan reviews, a signed city development agreement and a construction permit. Kraus Anderson and design partners said site mobilization is targeted for late March/early April and the build is planned as a roughly two-year project.
Get email alerts on the Capital Projects Jail topic
No spam. Unsubscribe anytime.
Danielle Reed and representatives from Kraus Anderson updated the board on the county's new jail project, reporting that state plan reviews and the city development agreement are complete and that the project has obtained the necessary permits to begin construction.
The nut graf: with state and city approvals in hand, the contractor said it is teed up to mobilize equipment and begin site work as weather permits, with a two-year construction timeline targeted.
Danielle said plan-review approvals are complete, including sign-offs from the State Department of Corrections, the Department of Health (kitchen review), plumbing plan review and the state plan reviewer for building-code items. "So that's really big news...we got the permit to move forward with construction," she said.
Kraus Anderson staff said equipment has been staged and that, weather permitting, site mobilization was expected around March 31 to the first week of April; structural precast panels were projected for mid-to-late July and a two-year build was the schedule presented. On budget, the design team reported roughly $300,000 in accepted value-management ideas so far and no material change to the overall budget to date.
Danielle and the contractor described a plan-review issue that required changing the specified skylights from triple acrylic dome units to insulated glass units and adding a capture screen near the glazing; the team estimated the skylight change and associated work could add roughly $100,000–$150,000 (they cited approximately $1,000 per skylight to switch materials). Danielle noted the state code exception for breakable skylights is being narrowed and that future jail projects might require an engineered smoke-management system that could add substantially more cost if required.
Ending: Commissioners thanked the team and asked a few follow-up questions about tariffs, material lock-ins and how contractors can secure materials; the team said the contract is a lump-sum contract and the contractor can, in some cases, pre-purchase and store materials to mitigate price volatility.