Commission approves $200,240 change order to add valley‑gutter work to overlay contract

2700226 · March 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved Change Order No. 1 to the FY25 mill‑and‑overlay contract, adding $200,240 and 45 calendar days to replace 2,956 linear feet of valley gutter across multiple streets, most notably Jack Maar and Summit/Valley segments.

The City Commission on March 18 unanimously approved a $200,240 change order to the newly awarded FY25 mill‑and‑overlay contract with Gator Grading and Paving LLC to add valley‑gutter removal and replacement across several streets.

City staff said the change order stems from favorable unit pricing in the low bid and allows the city to expand curb and valley‑gutter replacement without a separate procurement. The change order covers 2,956 linear feet of valley gutter; staff said 1,292 linear feet will be replaced on Jack Maar and 1,547 linear feet on Valley and Summit Drive combined.

Clay Watkins said the change will produce a more continuous replacement zone (instead of piecemeal patches), improving curb life and the finished product. Staff noted the change order adds 45 calendar days to the contract completion time.

The commission approved the change order by unanimous voice vote; staff said the total value to Gator Grading and Paving after the change order will be roughly $1.48 million when combined with the original award.

Next steps: work is to be scheduled to coordinate with paving and other capital activities; staff will report construction progress to the commission.