Board refers 20-year wastewater evaluation and Terrell Street utility replacement to Public Works committee
Summary
The board referred two infrastructure items — a state-required 20‑year engineering evaluation of the wastewater treatment and collection system and a full replacement plan for water/sewer and streets on Terrell Street — to the Public Works Committee for funding and scheduling discussion.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Assistant Engineer Ted Gillen asked the board to refer two infrastructure items to the Public Works Committee on March 17: a state-required 20‑year engineering evaluation of the wastewater treatment and collection system tied to the city’s operating permit, and a full replacement of water, sewer and street infrastructure on Terrell Street after repeated breaks.
Gillen and other members said the wastewater plant operating permit requires the 20‑year engineering study and that the Terrell Street corridor has experienced multiple breaks in the past two years; staff described repeated emergency repairs as more costly than a complete replacement. Aldermen representing the area and committee chairs said local businesses — named examples included Paisano’s and Delvinari’s Bakery — want a durable long-term fix rather than repeated patches.
Both items were referred to the Public Works Committee for further discussion of scope, funding and scheduling. Committee referral will allow staff to present cost estimates and funding pathways.