Germantown board awards two road contracts, adds contingencies
Summary
The board awarded the Village’s 2025 annual road program to Wolf Paving with a 10% contingency and a separate state‑assisted Rockfield Road reconstruction contract to Payne & Dolan; both awards passed on roll-call votes.
Get email alerts on the Infrastructure Roads topic
No spam. Unsubscribe anytime.
The Germantown Village Board on Monday approved two construction contracts for village roads.
The board awarded the 2025 Road Program to Wolf Paving for a base bid of $1,176,115 and approved an added 10% contingency, bringing the total authorization to $1,293,726.50. The contingency was added as part of an amendment to the original motion; trustees discussed that the contingency is customary to cover unforeseen construction price changes and engineering adjustments.
Separately the board awarded reconstruction of Rockfield Road to Payne & Dolan. The base award amount was $931,369; with contingency the motion recorded a total of $1,024,505.90. Village staff said the Rockfield Road work is one half of an ARIP (state grant) project that also includes Pleasant View Road; staff explained the board prioritized Rockfield first because of design and grant timing.
Why it matters: The Rockfield project is partially funded by the state’s ARIP program; staff said ARIP will reimburse 90% of eligible costs and the village (and the adjacent town for their share) will pay the remaining 10%. Trustees discussed coordination with an upcoming solar-farm construction and possible road impacts from heavy construction traffic and agreed to coordinate timing with the solar project developer.
Votes and details - Motion: Award 2025 Road Program construction to Wolf Paving and add a 10% contingency (total authorization $1,293,726.50). Outcome: Approved (roll-call; ayes recorded by the board). - Motion: Award Rockfield Road reconstruction to Payne & Dolan with contingency (total authorization $1,024,505.90). Outcome: Approved (roll-call; ayes recorded by the board).
Board members who spoke - Trustee Rick Miller moved to add the 10% contingency to the Wolf Paving award. He said the contingency was recommended at the public works meeting. - Several trustees asked staff whether awarding separate contracts (Wolf Paving for the annual program and Payne & Dolan for Rockfield) was normal; staff explained Rockfield is bid separately because it is part of an ARIP grant and has separate bid requirements.
Implementation and next steps - Staff will schedule pre-construction meetings with the winning contractors and coordinate timing and road condition documentation with the solar farm developer to minimize rework. - The village and town share of the Rockfield cost was explained as proportional to the road-footage allocation in the state road database.
Ending: Work will proceed this construction season; trustees asked staff to continue coordinating schedules and to monitor the work for any damage related to heavy construction traffic.