Firefly reports 8,550 active connections in Louisa, outlines remaining build work and timeline
Summary
Firefly representatives told the Louisa County Board of Supervisors that construction is largely complete in many service areas, that 8,550 customers are active in the county and that the project will likely need a contract extension to finish a small number of areas into next year.
Get email alerts on the Broadband Infrastructure topic
No spam. Unsubscribe anytime.
Firefly representatives gave the Louisa County Board of Supervisors an update on the company’s countywide fiber build on March 17, saying most construction is complete in multiple circuits and that 8,550 customers are actively connected in Louisa County.
The presentation outlined which substation circuits are in service, which remain in make-ready or splicing phases, and how multiple funding sources and partner networks factored into the work. "We have 8,550 Firefly connections today," Firefly representative Gary Wood said, and added the company is "in front of about 14,500 locations," producing a roughly 60 percent take rate where service is active.
The presentation and discussion
Wood and colleagues described three color-coded statuses on project maps: blue areas where construction and first-pass connections are complete; green areas where fiber is installed but splicing or final connections remain; and pink areas where data collection or small additional projects are needed. He told the board that the company expects to provide service to roughly 17,374 passings from the 2022 project and related earlier work, not including a separate 2024 project that adds roughly 434 locations and 16 miles of fiber.
Wood outlined funding and schedule: original CBC and CARES projects involved roughly $14 million, while the large outside-CBC phase was "almost $70,000,000" including county and state match, and the speaker estimated the total Firefly investment in the county will be on the order of $85–$90 million once finished. He said construction was slowed by winter weather and by federal funding processes on some federally funded segments; Firefly aims to run a pace of about 250 service activations a week in good weather.
Board questions and staff follow-up
Supervisors pressed for specific timing for small uncovered pockets and for areas that were handed back to Firefly by other jurisdictions. Gary Wood acknowledged a few small clusters still require additional work: one corner served under a different federal grant, an area dependent on Dominion handoffs, and isolated homes where mapping and incumbent provider availability complicated work. He said make-ready work should wrap in many circuits within weeks and that splicing and connection work will follow.
Several supervisors thanked the company for its responsiveness to constituents and asked staff to follow up on individual addresses. Wood encouraged residents to use Firefly’s availability lookup on the company website for up-to-date status or to contact county staff for specific follow-up.
Why it matters
County officials described the project as a multi-year, taxpayer- and grant-funded effort that materially changes broadband availability and expected economic outcomes across Louisa. The board and Firefly agreed they will request a project extension in May for a limited number of remaining segments; Wood said that asking for an extension does not mean the project is slowing down.
Looking ahead
Firefly told the board it will continue weekly connection targets and will finish the main construction this year while a few corner cases and handback areas may require work into next year. The company also said it is finishing public-facing maps and address lookup tools so residents can check their specific status.