Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure Contracts topic

No spam. Unsubscribe anytime.

City awards $15.02 million contract for East Riverfront Phase 1 after scope reductions

2685948 · March 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After low bids exceeded estimates, the commission approved a revised award to Owens/Ames/Kimball for Grand River East Riverfront Phase 1 with a not-to-exceed total of $17.97 million; the city said most funding comes from a DGRI greenway grant with local ARPA and capital match.

The city commission on March 11 approved a construction contract for the Grand River East Riverfront Phase 1 — a project to build riverside paths, green space and kayak access along the east riverfront near the amphitheater — approving a low-postaddendum award of $15,020,504 and a total not-to-exceed authorization of $17,970,196.

Why it matters: The project creates a roughly half-mile river-edge pathway, about 4.5 acres of green space, seating overlooking the river and a kayak launch adjacent to the under-construction amphitheater. City staff said the work will also provide circulation and an additional access point to the amphitheater.

Bids, scope changes and funding: Four bids were received; the lowest initial bid exceeded the engineer’s estimate by roughly $4.7 million. City staff and project partners (Downtown Grand Rapids Inc., DGRI, and consultants) reviewed options and recommended removing nonessential amenities — swing benches, certain pavers and a catenary lighting system — to reduce cost. After a post-bid addendum, the contract award was reduced to $15,020,504. The commission approved a not-to-exceed total of $17,970,196 to allow for contingency and change orders.

Funding sources: Staff said the project will be funded primarily by a $16.8 million greenway grant secured by DGRI, with the remainder coming from city capital improvement funds, American Rescue Plan Act (ARPA) funds and flood-wall bond funds.

Local participation: Staff noted there were no qualifying micro-local-business-enterprise (MLBE) bid discounts available for this award due to funding requirements tied to ARPA dollars; staff said they continue to encourage local contractor involvement through outreach programs but that capacity constraints and bid categories limited MLB participation for this contract.

Outcome: The commission approved the award and the funding authorization. Staff may revisit scope in the future if additional funding becomes available and could re-add certain amenities at that time.

Ending: Work will proceed under the awarded contract with contingency authorization; staff will continue outreach to encourage local participation on future contracts and will monitor costs as construction advances.