Council awards contract to relocate utilities ahead of Lapham Street bridge replacement
Summary
The council approved a contract to relocate utilities in advance of a federally funded bridge replacement; the low bid was roughly $382,482 and staff said the work must be completed before the bridge work begins in fall 2025.
Get email alerts on the Infrastructure Utilities topic
No spam. Unsubscribe anytime.
The Common Council voted to award a construction contract to relocate utilities in advance of the planned Lapham Street bridge replacement.
Why it matters: The bridge replacement is federally funded and scheduled to start in fall 2025; utilities that cross or run adjacent to the bridge must be relocated before the bridge contractor begins work.
Staff summary and contract award
Staff member Jason Herzog described the utility relocation package and said the city solicited bids for directional boring and consolidated relocation work to move sanitary force mains, electric lines and other utilities out of the future bridge footprint. The low bidder, Advanced Construction, submitted a bid of about $382,482; staff recommended awarding the contract after reference checks.
Herzog told council the work had a split cost allocation among municipal utilities and the electric utility, and that a budget amendment was included in the agenda to reflect the shared funding and to cover city staff costs needed for project management.
Council action
Council approved the contract award and associated budget amendment; the motion passed on a roll call vote with all members present voting in favor.
Quote from staff
“We reached out to Advanced Construction, talked with at least 6 of their references to confirm that they're capable of completing this work . . . and are recommending Advanced Construction to be a part of that,” Herzog said.
Next steps
Herzog said the relocations will take place ahead of the bridge construction window; staff will coordinate with the state and federal project partners and report progress to the council. The bridge work itself was described as starting in fall 2025 and continuing into 2026.