County seeks bids and advances several public‑works projects, including FEMA culvert repair and fish‑passage materials

2677139 · March 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works staff outlined a FEMA-funded culvert replacement bid, certified county forces final cost on a chip-seal job, awarded materials contracts for landfill tarps and fish‑passage structure, and noted an ARPA-funded wastewater plant contract.

Cowlitz County public‑works staff briefed commissioners on several capital and maintenance items on the consent agenda and a motion item intended to keep construction schedules on track.

County Engineer Susan Eugenas told the board the Italian Creek Road culvert replacement (milepost 1.9) is a FEMA‑funded project that was redesigned to meet fish‑passage requirements. Construction contract work is estimated at just over $600,000 with about $100,000 for construction management; the combined construction‑phase estimate presented to the board was about $740,000. The bid opening for that project was scheduled for April 13 at 1:30 p.m. in the Public Works building.

Eugenas also presented final costs for a county forces chip‑seal project on Camelot Court. State rules require counties to advertise work done by county crews when projects exceed a statutory threshold; the county’s final certified cost was $18,326.41 versus an original estimate of roughly $15,000.

Public works recommended awarding a materials purchase to Northwest Linings and Geo Textile Products for 28 reinforced polyethylene geomembranes (100 by 200 feet) for use at the landfill, at a total cost of $121,206.64. Two other bidders were deemed nonresponsive.

Eugenas described the Toodle Wastewater treatment plant upgrade, an ARPA‑funded project previously awarded to Tapani Incorporated; the county had moved to award that contract on Feb. 18, with Tapani the low bidder about $80,000 below the engineer’s estimate.

Finally, the board discussed awarding a materials contract to Contract Engineered Structures for structural steel and related materials for the Garlock Road Fish Passage Replacement Project. The materials contract amount was $167,958.15; staff said the separate materials contract was planned so fabrication could start promptly and meet the summer fish‑passage construction window. The fabricator will submit shop drawings, coordinate deliveries and provide a load rating because the span will be considered a bridge.

Ending: Public works staff said the materials purchases and fabrication work are within budget estimates and are intended to keep the projects on schedule to meet environmental windows and construction timelines.