Georgetown Municipal Water to fast-track Ettor/Adder Lane line for new church; council approves $80,050 engineering pass-through

2665075 · February 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The City Council approved $80,050 in additional engineering costs so the water utility can fast-track a 12-inch main extension to serve a proposed church campus on Iron Works Road.

The Georgetown Municipal Water and Sewer Service presented a request to the City Council on Feb. 10 to accelerate a portion of the larger South Side Storage Tank and distribution improvements so the system can provide the flow and pressure required by a newly proposed church campus.

Utility staff told the council the broader South Side Tank project is a multi-year effort combining a new storage tank with multiple distribution main upgrades across the southern service area. Because the full project’s schedule would not meet the church’s desired opening timeline (anticipated spring/summer 2026), staff proposed extracting and fast-tracking roughly 3,800 linear feet of new 12-inch main to eliminate two hydraulic dead-ends on Etter Lane and deliver the needed service level.

Engineering firm fees to create separate bid documents and manage a fast-track contract were estimated at $80,050. Georgetown Municipal asked the council to approve those additional engineering/administration costs as a pass-through; the church has agreed to reimburse the utility under a reimbursement agreement tied to monthly invoice progress. The council approved the request by voice vote.

Utility Director Chase (presenting) said the split requires duplicate contract documents and additional construction-administration resources but will let the church open on its schedule while preserving the broader South Side project’s integrity. Council members asked for a permit and construction timeline; the director said permitting is expected to be straightforward but review times at the Kentucky Division of Water are variable, so he would provide a more specific schedule to council by email.

The council approved execution of a reimbursement agreement and the engineering pass-through; the church will pay the utility for the added engineering/administration costs. No city capital appropriation was needed beyond the utility’s existing project funding; the utility will invoice the church for the $80,050 if the final engineering cost equals that estimate.