Booking-room project nears substantial completion; architect and contractor closeout responsibilities outlined

5748441 · July 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County project manager reported the booking-room renovation is about 85% complete, with $58,252 in change orders to date, a remaining contractor balance of $222,001.32 and architectural professional services totaling $253,008.10; staff outlined a punch-list schedule, TDLR architectural barrier inspection deadline and final closeout steps.

Potter County project staff told the Commissioner’s Court on July 14 that the booking-room renovation is nearing substantial completion and outlined remaining closeout steps, outstanding balances and state inspection requirements. Construction manager Mike (staff) reported the OPREX construction contract is about 85% complete and that change orders issued total $58,252. He said, after pay request No. 9, the contractor balance stood at $222,001.32 against an original guaranteed maximum price of about $1.6 million; staff said contingency funds have…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans