Hastings staff outlines 1- and 6‑year street improvement plan, bids due for hike‑and‑bike project
Summary
City staff presented the 2025–26 one‑and‑six year street improvement plan, including asphalt resurfacing, curb work, quiet‑zone paperwork with the Federal Railroad Administration, a Twelfth Street restriping concept and a state‑led Southeast corridor project with an 80/20 cost share.
Lee (staff member) presented the Hastings Planning Commission with the city’s proposed 1‑ and 6‑year street improvement plan on Tuesday, laying out projects planned for completion this calendar year and larger projects included in the 2025–26 budget.
The plan lists two paving districts (Elm Meadows and Laughlin Meadows), concrete repair on Laird Avenue (Ninth to Eleventh), Woodland Avenue, D Street near Brickyard Park, curb and gutter work on Chicago Avenue (E to F) and Lincoln Avenue (Burlington Northern tracks to South Street). "That project is in conjunction with the hike and bike trail," Lee said of the E Street repaving, adding that bids for the trail/street work are…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat