Committee approves Minn Kota reimbursement estimate and awards Raymond Township mobility contract to low bidder
Summary
The finance committee approved two contracting actions: reimbursement to Minn Kota Power for construction work estimated at $3.4 million and an award for a Raymond Township mobility project to RJ Zaveral & Sons for $579,297.51 after five bids were received.
The Metro Flood Diversion Authority Finance Committee on July 23 approved two contracting actions tied to ongoing diversion work: a reimbursement authorization for Minn Kota Power and the award of a Raymond Township mobility contract. Chris Beykegard, the authority engineer, told the committee the Minn Kota item corresponds to the previously approved Minn Kota budget…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat