Commission accepts Phase 2 street-improvement project and authorizes release of retainage contingent on punch-list completion

5679302 · July 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission accepted final completion of the Phase 2 street-improvement contract, approved a final change order that raises the contract to about $2.908 million, and authorized release of retainage once outstanding punch-list items are finished.

The Breckenridge City Commission voted July 1 to accept final completion of the Phase 2 street-improvement project and to authorize release of retainage contingent on receipt of required closeout documentation and completion of punch-list items.

Staff said the original contract began at $2,405,233.20 and that a final quantity-verification change order (Change Order No. 3) added $77,978.11 for a total construction completion contract amount of $2,908,049.94. The contract contractor provided closeout documents; staff reported a small number of punch-list items remained and recommended release of retainage once those items were confirmed complete. A one-year warranty on the work begins from the date of substantial completion.

City staff noted one outstanding punch-list item involved a tie-in on Harvey Drive North at Williams and said crews were on-site to complete that work. The commission authorized the city manager to execute the paperwork to accept the project and release retainage when staff confirms closeout.

Discussion vs. decision: the commission voted to accept the project and to permit release of retainage contingent on staff verification that the punch-list and closeout documents are complete.