Supervisors retroactively approve $103,782 emergency server purchase for Independence data center
Summary
County IT staff obtained board approval to retroactively ratify a $103,782 emergency purchase of Nutanix server nodes for a backup at Independence Data Center after overheating issues threatened mission-critical finance systems at the Bishop facility.
Get email alerts on the Infrastructure And It topic
No spam. Unsubscribe anytime.
Abhi (last name not stated), Acting Chief Information Officer, told the Board on Aug. 19 that a mission-critical finance system (Finance Enterprise) was at risk following environmental-control failures at the county’s primary data center in Bishop. To secure redundancy, the county made an emergency purchase of Nutanix server nodes for the Independence Data Center and sought retroactive board approval.
Abhi said the county had budgeted for a backup at Independence but the immediate overheating risk prompted an emergency purchase. He asked the board to declare Roundstone Solutions a sole-source provider and retroactively authorize a purchase order not to exceed $103,782 for the Independence Data Center Nutanix server nodes.
Supervisors discussed the importance of redundant infrastructure and approved the retroactive authorization. The purchase was described by staff as necessary to ensure continuity for payroll, accounts payable, accounts receivable and other finance reporting functions that depend on the Finance Enterprise application.
Action taken: The board approved the recommended retroactive authorization and sole-source designation and ratified the county administrative officer’s emergency purchase.