Commission hears progress report on tower construction and runway rehabilitation
Summary
The commission received an update that tower construction is proceeding (including night work) and is tracking under budget; the runway rehabilitation work is complete except for final markings, which are pending a 30-day cure period and scheduling with the contractor Emory SAP.
Get email alerts on the Airport Capital Projects topic
No spam. Unsubscribe anytime.
Commissioners received a capital-project update on June 19 showing tower work progressing under budget and runway rehabilitation nearing completion.
Garber, a staff member providing the project update, told the commission the tower construction is scheduled for night work to avoid interfering with air traffic and that project costs are currently "tracking under budget." He said the plan includes acquiring a backup generator with available funds. On runway rehabilitation, Garber said Emory SAP has finished the pavement work and "the only thing outstanding is the final markings." He said the contractor must wait the required 30-day cure before the final markings can be applied and that staff are coordinating scheduling with Emory SAP.
Commissioners asked questions about the tower and runway timing and budget; Garber said Greg Collier, the chair, is out this week and will return next month. The update was informational; no formal action or appropriation was taken during the meeting.