City says Brazier Bayou dredging will pause about two weeks while contractor repositions barge
Summary
Public works staff told the council that dredging in Brazier Bayou is temporarily paused while the contractor brings a smaller barge in from another job; an intermediate hydrographic survey will be done during the pause.
Get email alerts on the Infrastructure Dredging topic
No spam. Unsubscribe anytime.
A public-works update at the Biloxi budget workshop reported an expected two-week pause in dredging operations in the Brazier Bayou project while the contractor brings in a smaller barge to continue work. Project staff said the contractor has completed dredging with their large barge and must stage a smaller barge from another jobsite; staff told councilmembers residents may observe hydrographic survey crews during the interim. Why it matters: delays affect project timeline for navigation, stormwater or habitat outcomes tied to the dredging contract and can affect scheduling of adjacent work. Details from the update: - Staff said the contractor told city staff they are finished dredging with the large barge and need one to two weeks, and staff said they would use two weeks as a maximum estimate for the pause. - During the pause residents may see hydrographic survey crews and other personnel conducting intermediate surveys to assess dredging progress. - Staff framed the pause as routine logistics while the contractor brings equipment from another job and said they will monitor and notify residents as work resumes. Next steps: monitoring and an interim hydrographic survey; staff will report back if the schedule changes.