Council approves IGA amendment for Fourth Street–Lockett roundabout as costs rise to $6.6M

5582661 · August 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Flagstaff approved an amendment to an intergovernmental agreement with ADOT for design and construction of the Fourth Street–Lockett roundabout; estimated total cost increased to about $6.6 million and the city share rose to roughly $4.7 million, staff said.

Flagstaff City Council on April 2 approved Amendment No. 2 to an intergovernmental agreement (IGA) with the Arizona Department of Transportation for design and construction of a roundabout where Fourth Street meets Cedar Avenue/Lockett Road.

Project history and cost: Alec Latino, capital improvements project manager, told council the highway-safety grant remains $1.9 million from the Highway Safety Improvement Program and that the total project cost had risen to an estimated $6.6 million. “The city share has gone up to $4,700,000,” Latino said, and staff told council that the increase largely reflects construction cost escalation, higher engineer’s estimates, added right-of-way purchases and temporary construction easements (TCEs), and additional design and project administration needs. The right-of-way costs included a property purchase and demolition near East Lockett.

Schedule and coordination: Latino said construction was pushed into spring 2025 to allow final design and to accommodate right-of-way work. He and a public-works representative said the city plans to avoid overlapping major nearby closures; staff intends to complete the Linda Vista work before the roundabout construction to minimize concurrent traffic impacts.

Why it matters: staff said the intersection had been identified as a hazardous area and thus qualified for federal safety funds; the roundabout is intended to reduce collision risk and improve traffic flow along a corridor used by regional traffic.

Votes and next steps: Council adopted the resolution to amend the IGA and authorized staff to proceed with advertisement for construction once plans are finalized. Staff will complete 100% design, finalize right-of-way and move to bid for a spring 2025 construction window. The item will return to council only for routine updates unless additional funding or design changes are required.