Westgate Authority outlines Kratos timelines, sewer phases and federal funding bids

5580970 · August 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Westgate Authority representative Kent Parisian told county commissioners that Kratos construction could start this month, described multi‑phase sewer work tying new buildings into existing systems, and said congressional directed spending and other grants are being pursued to connect nearby towns.

Kent Parisian, a staff member providing the Westgate update, told the Davies County Board of Commissioners that Kratos’ first building is scheduled to begin concrete work Aug. 15, with a connected steel building to follow and a projected completion for Kratos in June 2026. The update said a microelectronics training hub ribbon cutting is set for Sept. 29 at the former SAIC building (now EC2B) and that the RCE building is planned to begin after a September groundbreaking and complete in December 2026. Parisian…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans