Broussard declares Main Street Phase 3B substantially complete, 40‑foot light poles remain
Summary
Council voted to declare Broussard Main Street Phase 3B substantially complete, allowing the contractor to pursue retainage release while installation of 40‑foot light poles is still pending; Southern Construction completed core elements and Sunco will install poles on a separate schedule.
Get email alerts on the Infrastructure Roadside topic
No spam. Unsubscribe anytime.
The City of Broussard on Aug. 12 voted to declare Broussard Main Street Phase 3B substantially complete, clearing most of the work for retainage release while leaving the 40‑foot light poles as outstanding items to be finished in a follow‑on step.
Joseph Marino of Duplantis Engineering presented photos and a progress summary, saying the project transformed a previously eroded area near the firework station with subsurface drainage, a 10‑foot multiuse path and new sidewalks that connect Allison Parkway to South Bernard and on toward Patterson Parkway.
Marino said most punch‑list items have been addressed and that the contractor, Southern Construction, requested the substantial completion certificate to free retainage on the completed work. “This certificate substantial completion is good for all work except for 40 foot light poles,” Marino said, noting delays in materials and that Sunco has been paid to install poles on Celebrity to Iverson Parkway and that Southern Construction will complete remaining pole work thereafter.
Marino told the council the city expects a clear lien release within 45 days once the substantial completion is recorded and that Sunco will perform the pole installation while other beautification work continues on Main Street.
There was no public comment on the item. Council members conducted a roll‑call and approved the recommendation to declare the project substantially complete.
Speakers at the item included Joseph Marino (Duplantis Engineering). The presentation referenced the contractor Southern Construction and subcontractor Sunco as active parties.
Why it matters: Declaring substantial completion allows the contractor to pursue retained funds for completed work and clears the way for final lien releases; outstanding elements remain limited to high‑mast lighting installations.
Next steps: City staff will record the substantial completion certificate, process retainage and coordinate remaining pole installation with Sunco and Southern Construction.