Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure Payments topic

No spam. Unsubscribe anytime.

Board approves multiple contractor pay estimates, final retainage release and a concrete license

5579823 · August 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board of Public Works approved pay estimates totaling multiple hundreds of thousands of dollars across infrastructure projects, released a $5,000 retainage for a 2023 street construction project, and approved a concrete license for Ross Construction LLC.

The Board of Public Works on Aug. 12 approved several pay estimates and a concrete license for Ross Construction LLC as part of routine contract administration and project closeouts.

Payments approved included a $76,190.98 payment for the 2025 sidewalk repair project A (S.D. Ellenbecker pay estimate no. 3), $660,666.83 for work to date on the Washington Street siphon replacement project (A-1 Excavating pay estimate no. 1), $523,056.96 for 2025 Street Construction Project B (Switlick & Sons pay estimate no. 4), and $472,915.50 for 2025 asphalt paving project A (American Asphalt pay estimate no. 1). The board also approved releasing $5,000 in retainage to close out the 2023 Street Construction project covering Day, Grant and Henrietta streets from Hassans Incorporated; staff said restoration holdback was adequate and recommended releasing the total retainage.

Inspectors reviewed or approved the listed estimates: Matt Guptail was cited as approving the sidewalk repair estimate; Kurt DeBoer as the inspector recommending Project B payment; and Brian Pettit was referenced as the project inspector for the asphalt paving item. Board members moved and seconded motions to approve each payment and the retainage release; each motion carried on an affirmative voice vote. The board also approved a concrete license for Ross Construction LLC after a board member indicated they had reviewed it.

The transcript does not include contract numbers, completion timelines, retainage-release conditions other than restoration being adequate, nor details on remaining contract scopes or warranties. No dissenting votes or public commentary on these items are recorded in the meeting excerpt.