Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Parks Recreation Projects topic

No spam. Unsubscribe anytime.

City approves $42,698 change order and 103‑day extension to stabilize Cane Creek Park pickleball courts

5580263 · August 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Cookeville council approved a $42,698.15 change order with Steelhead Building Groups to undercut and stabilize the pickleball court pad at Cane Creek Park and extended the project completion by 103 days; staff said work would resume Aug. 21 and complete by October.

Cookeville — The Cookeville City Council on Aug. 7 approved a change order with Steelhead Building Groups totaling $42,698.15 to stabilize the pad for new pickleball courts at Cane Creek Park and granted a 103‑day extension to the project schedule.

Why it matters: The change order addresses soil and subsurface conditions identified during construction and is intended to correct the contractor’s path and allow the courts project to resume safely.

Public works staff and the project manager summarized delays and said the change order will undercut unstable material and import new, compacted fill. "This is a change order that would help us stabilize the pad, by doing some undercutting and bringing in new materials," a staff member said. The change order adds 103 days to the original contract; staff said the contractor would remobilize Aug. 21 and the project would be completed by October.

Council members praised staff coordination. "Good work at city for jumping in here and getting this job done," one council member said, and another said the city had worked hard to ensure the job is done correctly and with high quality.

Council action: A motion to approve the change order was made, seconded and passed 5‑0. The motion authorized the change order amount and contract time extension; no separate motion about funding reallocation was recorded on the transcript.

What happens next: Construction is scheduled to resume after contractor mobilization; staff will oversee stabilization work and project completion under the extended schedule. Any further contract changes would require council review.