County to renew Tyler support, lease CoreSite space and move GIS to ROK Technologies

5579058 · August 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

IT staff requested authorization for three items: a Tyler Technologies maintenance renewal for $192,685, a CoreSite colocation lease ($28,500/year), and a migration of GIS infrastructure to ROK Technologies for $226,040 in year one.

County information-technology staff presented three technology procurements and a committee update about a separate C3AI review.

1) Tyler Technologies annual support: Staff requested authorization to pay $192,685 for annual maintenance of the county—s core tax-billing and computer-aided mass appraisal software supplied by Tyler (referred to in the meeting as "Tyler/IAS World"). Presenters said the fee is a slight percentage increase over last year and is not a new purchase. A commissioner asked for the exact increase and staff agreed to provide that figure before the next meeting.

2) CoreSite colocation lease: The county's broadband utility has a colocation presence in Atlanta (55 Marietta). JT Communications previously held the agreement but is no longer an entity; CoreSite now provides colocation services. Staff recommended a year-to-year lease at a recurring monthly cost of $23.75 per unit (total $28,500 per year) to maintain hub connectivity with service providers. Staff said the expense could come from Broadband's operating funds.

3) GIS infrastructure migration to ROK Technologies: The county proposed replacing an on-premises GIS server solution with a remote, cloud-hosted service from ROK (ROK Technologies), a provider recommended by Esri for its GIS hosting and managed-administration capabilities. Staff described benefits as improved disaster recovery, resiliency and access, and said the first-year cost would be $226,040 to be funded from GIS's 2025-2026 budget; future year costs would be budgeted by GIS. Staff said some past costs (about $113,000 budgeted to Esri for on-prem support) would be eliminated, and another anticipated $90,000 IT purchase had been deferred in expectation of this migration, meaning the net budget impact could be near a wash over time. A commissioner requested a cost comparison and a swap (detailed cost comparison) before the next meeting; staff agreed to provide that information.

Separately, committee members reported that the METI committee met with C3AI for a software demonstration and is conducting due diligence; the committee will report back to the Board of Commissioners at a later date.

All three items were moved toward consent; staff agreed to provide additional cost comparisons and increases at the next meeting.