Council approves $20,000 change order for Colliers Ferry pump station; project largely FEMA-funded, near completion

5578680 · August 6, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized change order No. 14 — about $20,000 — to add a traffic attenuation device, gate and camera pole to the Colliers Ferry pump station project. Staff said the project is largely FEMA-funded and is nearing construction completion.

Beaumont City Council approved a change order to the Colliers Ferry pump station contract to add traffic- and site-security measures, officials said, as the large mitigation project nears completion.

City staff said the change order under consideration — roughly $20,000 — covers a traffic attenuation device and a gate to improve safety where Pine Street meets the pump station entrance, plus a pole for security cameras to extend coverage of the pump station and adjacent Colliers Ferry Park. The project manager told council the total Colliers Ferry project is a complex undertaking with an estimated value near $25 million.

Staff reported that approximately 90% of the Colliers Ferry project is funded by FEMA as part of Harvey recovery mitigation, with roughly 7.5% covered by state funds. The change order included credit line items that reduced some costs elsewhere in the contract; staff said they will reconcile remaining line items during project closeout.

Council heard that construction work is approaching final stages: staff said they expect construction activities to be finished by September and that some pump-station equipment would remain idle until related waterline work on Pine Street is complete (staff estimated operations readiness for that pipeline as February–April next year). Council approved the change order; staff said a final reconciliation change order would follow at project closeout.

The amendment aims to improve public safety and site security as the project is readied for operation and long-term maintenance.