Facilities staff say township rejection forced milling and paving at Richboro Elementary; change orders reported

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The district reported a deduct change order of $14,441 for unused allowances and a $36,492.50 change order for milling and paving after the township rejected the contractor's pavement-marking removal; staff said the contractor followed PennDOT standards but the township required milling and paving to meet local expectations.

Facilities staff told the Council Rock School District Facilities Committee on Thursday that Richboro Elementary School required a follow-up change order after the township rejected the contractor’s pavement-marking removal method. Linda Khan, a district staff member, said the general contractor originally removed conflicting pavement markings using a PennDOT-approved method specified in contract documents. “The method that they used was in agreement with PennDOT standards,” Khan said. The township, however, rejected that approach and required the work to be milled and paved; the district paid a change order for milling and paving in the amount of $36,492.50. Khan also reported a deduct change order to Guy M. Cooper for unused allowance money in the amount of $14,441. She said the milling and paving were completed on Aug. 4 or 5. Khan told the committee the district coordinated with the township to avoid having the township hold escrow for incomplete work and that future project specifications will avoid specifying eradication of lines in favor of milling and paving where appropriate. The transcript does not record a formal committee vote on the change orders during the excerpt provided.